Violation Detail
Standard Cited: 19100269 C Electric Power Generation, Transmission, and Distribution.
This violation item has been deleted.
Inspection Nr: 913624.015
Citation: 01003
Citation Type: Serious
Abatement Date: 11/20/2013 2
Initial Penalty: $4,900.00
Current Penalty: $0.00
Issuance Date: 10/24/2013
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC): A
Gravity: 10
Report ID: 0111100
Contest Date: 01/07/2014
Final Order: 05/26/2014
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 05/26/2014 | $0.00 | 11/20/2013 | Serious | |
| Penalty | C: Contested | 01/22/2014 | $4,900.00 | 11/20/2013 | Serious | |
| Penalty | Z: Issued | 10/24/2013 | $4,900.00 | 11/20/2013 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.269(c): "Job briefing." The employer shall ensure that the employee in charge conducts a job briefing with the employees involved before they start each job. The briefing shall cover at least the following subjects: hazards associated with the job, work procedures involved, special precautions, energy source controls, and personal protective equipment requirements. New Limerick Jobsite - The job briefing involving the hazards associated with the job, work procedures involved, special precautions, energy source controls, and personal protective equipment requirements was inadequate. On or about 06/21/2013, a Second Class "A" Lineman who responded to a residential power outage at approximately 9:00 PM, was electrocuted when his left shoulder contacted a hanging energized 14,400 volt primary wire in an overgrown wooded area.