Violation Detail
Standard Cited: 19260451 E09 IV General requirements.
Inspection Nr: 912641.015
Citation: 01001B
Citation Type: Serious
Abatement Date: 10/03/2013 2
Initial Penalty: $3,080.00
Current Penalty: $0.00
Issuance Date: 09/09/2013
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 10
Report ID: 0316100
Contest Date:
Final Order: 10/22/2013
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 10/22/2013 | $0.00 | 10/03/2013 | Serious | |
Penalty | Z: Issued | 09/09/2013 | $3,080.00 | 10/03/2013 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1926.451(e)(9)(iv): Cross braces on tubular welded frame scaffolds were used as a means of access or egress. a) On June 18, 2013 and at times prior thereto; front of building, employees were observed climbing the cross braces to access other areas on the scaffold system. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.