Violation Detail
Standard Cited: 19100219 C04 I Mechanical power-transmission apparatus.
Inspection Nr: 909643.015
Citation: 01001
Citation Type: Other
Abatement Date: 10/21/2013 2
Initial Penalty: $5,400.00
Current Penalty: $0.00
Issuance Date: 09/24/2013
Nr Instances: 4
Nr Exposed: 1
Related Event Code (REC):
Gravity:
Report ID: 0419400
Contest Date:
Final Order: 10/31/2013
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 10/31/2013 | $0.00 | 10/21/2013 | Other | |
| Penalty | Z: Issued | 09/24/2013 | $5,400.00 | 10/21/2013 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.219(c)(4)(i): Projecting shaft ends shall present a smooth edge and end and shall not project more than one-half the diameter of the shaft unless guarded by nonrotating caps or safety sleeves. (a) On or about July 2, 2013 projecting shaft ends were not guarded at the following locations: 1) collecting belt at the coal feed bins 2) pugg mill feed belt 3) weigh bridge/scale belt 4) fly ash silo In the Alternative: 29 CFR 1926.307(c)(4)(i): Projecting shaft ends shall present a smooth edge and end and shall not project more than one-half the diameter of the shaft unless guarded by nonrotating caps or safety sleeves. (a) On or about July 2, 2013 projecting shaft ends were not guarded at the following locations: 1) collecting belt at the coal feed bins 2) pugg mill feed belt 3) weigh bridge/scale belt 4) fly ash silo