Violation Detail
Standard Cited: 19100303 F02 General.
Inspection Nr: 904816.015
Citation: 01010
Citation Type: Serious
Abatement Date: 08/14/2013 2
Initial Penalty: $4,000.00
Current Penalty: $3,400.00
Issuance Date: 08/08/2013
Nr Instances: 6
Nr Exposed: 60
Related Event Code (REC):
Gravity: 5
Report ID: 0936500
Contest Date:
Final Order: 09/03/2013
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/03/2013 | $3,400.00 | 08/14/2013 | Serious | |
Penalty | Z: Issued | 08/08/2013 | $4,000.00 | 08/14/2013 | Serious |
Text For Citation: 01 Item/Group: 010 Hazard:
29 CFR 1910.303(f)(2): Each service, feeder, and branch circuit, at its disconnecting means or overcurrent device, was not legibly marked to indicate its purpose, nor located and arranged so the purpose was evident: a) Building 9 outside circuit breaker box was not labled. b) Building 63, inside circuit breaker box next to steam room, the circuit breakers were mis-labled. c) Building 10, 11, 64 including but not limited to other building circuit breaker boxes and circuit breakers were mislabled or not marked at all.