Violation Detail
Standard Cited: 19100269 M03 V Electric Power Generation, Transmission, and Distribution.
This violation item has been deleted.
Inspection Nr: 900343.015
Citation: 01002
Citation Type: Serious
Abatement Date: 08/02/2013
Initial Penalty: $7,000.00
Current Penalty: $0.00
Issuance Date: 06/17/2013
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 10
Report ID: 0729300
Contest Date: 06/26/2013
Final Order: 07/17/2014
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 07/17/2014 | $0.00 | 08/02/2013 | Serious | |
| Penalty | C: Contested | 07/03/2013 | $7,000.00 | 08/02/2013 | Serious | |
| Penalty | Z: Issued | 06/17/2013 | $7,000.00 | 08/02/2013 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.269(m)(3)(v): After the applicable requirements in paragraphs (m)(3)(i) through (m)(3)(iv) of this section have been followed, the employee in charge of the work did not obtain a clearance by the system operator, and the lines and equipment to be worked were not tested to ensure that they were de-energized: On or about April 11, 2013, during storm restoration, an employee was electrocuted while on a utility pole and contacted a 7200 V primary line. The primary line had not been tested to ensure it was de-energized.