Standard Cited: 19100147 F04 The control of hazardous energy (lockout/tagout).
Inspection Nr: 899225.015
Citation: 01004
Citation Type: Serious
Abatement Date: 10/07/2013 2
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 09/11/2013
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 10
Report ID: 0521700
Contest Date:
Final Order: 09/30/2013
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 09/30/2013 | $7,000.00 | 10/07/2013 | Serious | |
| Penalty | Z: Issued | 09/11/2013 | $7,000.00 | 10/07/2013 | Serious |
Text For Citation: 01 Item/Group: 004 Hazard:
29 CFR 1910.147(f)(4): During shift or personnel changes, specific procedures were not utilized to ensure the continuity of lockout or tagout protection, including provision for the orderly transfer of lockout or tagout devices between off-going and oncoming personnel: a. Facility - On or about May 16, 2013, specific procedures for the continuity of lockout protection and orderly transfer of lockout devices between off-going and oncoming personnel were not established. Employees were thereby exposed to the hazards associated with the unexpected energization of equipment.