Violation Detail
Standard Cited: 19260600 A06 I Equipment.
Inspection Nr: 844083.015
Citation: 01003
Citation Type: Serious
Abatement Date: 05/10/2013 2
Initial Penalty: $4,900.00
Current Penalty: $4,900.00
Issuance Date: 05/06/2013
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): A
Gravity: 10
Report ID: 0524530
Contest Date:
Final Order: 06/03/2013
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 05/06/2013 | $4,900.00 | 05/10/2013 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1926.600(a)(6)(i): For lines rated 50kV or below, a minimum of 10 feet was not maintained between the energized line and the equipment. Employees were exposed to electrical shock hazards when the clearance between the 7.5 kV lines and the Caterpiller Excavator, Model 328D, was not maintained at least 10 feet.