Violation Detail
Standard Cited: 19261408 A01
Inspection Nr: 640558.015
Citation: 01001
Citation Type: Serious
Abatement Date: 03/04/2013 4
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 02/26/2013
Nr Instances: 6
Nr Exposed: 5
Related Event Code (REC): A
Gravity: 10
Report ID: 0523900
Contest Date: 03/20/2013
Final Order: 02/10/2014
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 02/10/2014 | $7,000.00 | 03/04/2013 | Serious | |
| Penalty | C: Contested | 03/26/2013 | $7,000.00 | 03/04/2013 | Serious | |
| Penalty | Z: Issued | 02/26/2013 | $7,000.00 | 03/04/2013 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.1408(a)(1) The employer must identify the work zone for power line safety with equipment operations: (a) US Interstate Highway 94, between mile markers 28 and 41, of Wisconsin Department of Transportation project # 1022-07-74; The employer does not identify the work zone for overhead power line hazards where employees uses a self-contained pile driver truck that has a 16 foot 9 inch vertical mast, such as, but not limited to: (1) Exposure site # 1: Vicinity of US Interstate Highway 94 and 650th Avenue, between mile markers 38 and 39, on the south shoulder of the eastbound lane, Wisconsin Department of Transportation project # 1022-07-74, between work stations 815 and 817, such as occurred on or before August 28, 2012, and (2) Exposure site # 2: Vicinity of US Interstate Highway 94 and County Highway K, between mile markers 37 and 38, on the north shoulder of the westbound lane, Wisconsin Department of Transportation project # 1022-07-74, between work stations 752 and 754, such as occurred on or before August 29, 2012, and (3) Exposure site # 3: Vicinity of US Interstate Highway 94 and 650th Avenue, between mile markers 38 and 39, on the north shoulder of the westbound lane, Wisconsin Department of Transportation project # 1022-07-74, between work stations 815 and 817, such as occurred on or before September 5, 2012, and (4) Exposure site # 4: Vicinity of US Interstate Highway 94 and 390th Street, between mile markers 40 and 41, on the north shoulder of the westbound lane, Wisconsin Department of Transportation project # 1022-07-74, between work stations 885 and 887, such as occurred on or before September 10, 2012, and (5) Exposure site # 5: Vicinity of US Interstate Highway 94 and 390th Street, between mile markers 40 and 41, on the median shoulder of the westbound lane, Wisconsin Department of Transportation project # 1022-07-74, between work stations 885 and 887, such as occurred on or before September 12, 2012, and (6) Exposure site # 6 (electrocution location): Vicinity of US Interstate Highway 94 and 650th Avenue, between mile markers 38 and 39, on the median shoulder of the eastbound lane, Wisconsin Department of Transportation project # 1022-07-74, between work stations 815 and 817, such as occurred on September 17, 2012.