Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 593778.015
Citation: 02001
Citation Type: Other
Abatement Date: 01/15/2013 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 10/15/2012
Nr Instances: 1
Nr Exposed: 11
Related Event Code (REC):
Gravity:
Report ID: 0419700
Contest Date:
Final Order: 11/07/2012
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 11/07/2012 | $0.00 | 01/15/2013 | Other | |
| Penalty | Z: Issued | 10/15/2012 | $0.00 | 11/28/2012 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: a. On or about August 25, 2012, the employer did not complete annual reviews of all energy control procedures.
Translate