Violation Detail
Standard Cited: 19100333 C03 Selection and use of work practices
Inspection Nr: 588966.015
Citation: 02001A
Citation Type: Willful
Abatement Date: 3
Initial Penalty: $56,000.00
Current Penalty: $56,000.00
Issuance Date: 02/20/2013
Nr Instances: 2
Nr Exposed: 2
Related Event Code (REC): A
Gravity: 10
Report ID: 0418800
Contest Date: 02/22/2013
Final Order: 01/22/2015
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | R: Review Commission | 01/22/2015 | $56,000.00 | Willful | ||
| Penalty | C: Contested | 02/25/2013 | $56,000.00 | Willful | ||
| Penalty | Z: Issued | 02/20/2013 | $56,000.00 | Willful |
Text For Citation: 02 Item/Group: 001A Hazard:
29 CFR 1910.333(c)(3): When work was to be performed near overhead lines, the lines were not de-energized and grounded, nor were other protective measures provided before work was started: On or about 8/21/2012, at 2660 SW 13th Avenue, Fort Lauderdale, FL, the employer did not ensure that overhead power lines were de-energized prior to work being started.