Violation Detail
Standard Cited: 19260850 E Preparatory operations.
Inspection Nr: 587409.015
Citation: 01007
Citation Type: Serious
Abatement Date: 02/25/2013 2
Initial Penalty: $3,080.00
Current Penalty: $2,310.00
Issuance Date: 02/15/2013
Nr Instances: 1
Nr Exposed: 7
Related Event Code (REC): A
Gravity: 10
Report ID: 0626600
Contest Date: 03/05/2013
Final Order: 09/19/2013
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | R: Review Commission | 09/19/2013 | $2,310.00 | 02/25/2013 | Serious | |
| Penalty | C: Contested | 03/05/2013 | $3,080.00 | 02/25/2013 | Serious | |
| Penalty | Z: Issued | 02/15/2013 | $3,080.00 | 02/25/2013 | Serious |
Text For Citation: 01 Item/Group: 007 Hazard:
29 CFR 1926.850(e): It had not been determined if any type of hazardous chemicals, gases, explosives, flammable materials or similar dangerous substances had been used in any pipes, tanks, or other equipment on the property. The presence of such substances were apparent and the hazard was not eliminated before demolition was started. The employer does not ensure that dangerous substances are tested or eliminated before demolition is started. This violation occurred on or about August 19, 2012, at the Watco Mechanical Services interior blast building where employees were exposed to explosion and fire hazards when using a cutting torch for demolition activities where there was an accumulation of combustible dust throughout the interior blast building that was not eliminated prior to demolition activities. Pursuant to 29 C.F. R. 1903.19, within ten (10) calendar days of the abatement date, the employer must submit documentation showing that it is in compliance with the standard, including describing the steps that it is taking to ensure that dangerous substances are tested or eliminated before demolition is started.