Violation Detail
Standard Cited: 19100333 B01 Selection and use of work practices
Inspection Nr: 473118.015
Citation: 01003
Citation Type: Serious
Abatement Date: 11/05/2012 2
Initial Penalty: $2,800.00
Current Penalty: $1,400.00
Issuance Date: 10/29/2012
Nr Instances:
Nr Exposed: 4
Related Event Code (REC):
Gravity: 10
Report ID: 0626700
Contest Date:
Final Order: 11/16/2012
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 11/16/2012 | $1,400.00 | 11/05/2012 | Serious | |
| Penalty | Z: Issued | 10/29/2012 | $2,800.00 | 11/05/2012 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.333(b)(1): The employer did not ensure that exposed deenergized parts were locked out and tagged in accordance with paragraph (b) and treated them as energized parts. At the Southern most portion of the job site on June 15, 2012, the employer did not ensure that deenergized parts that the employee would be exposed to were locked out and tagged out, exposing employees to electrical hazards such as arc flash.
Translate