Violation Detail
Standard Cited: 19100305 B01 II Wiring methods, components, and equipment for general use.
Inspection Nr: 456154.015
Citation: 01004A
Citation Type: Serious
Abatement Date: 12/05/2012 2
Initial Penalty: $1,785.00
Current Penalty: $2,380.00
Issuance Date: 12/04/2012
Nr Instances: 3
Nr Exposed: 1
Related Event Code (REC): A
Gravity: 1
Report ID: 0626000
Contest Date:
Final Order: 12/18/2012
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 12/18/2012 | $2,380.00 | 12/05/2012 | Serious | |
| Penalty | Z: Issued | 12/04/2012 | $1,785.00 | 12/05/2012 | Serious |
Text For Citation: 01 Item/Group: 004A Hazard:
29 CFR 1910.305(b)(1)(ii): Unused openings in boxes, cabinets, or fittings were not effectively closed: Employees were exposed to electrical shock due to unused openings in the electrical breaker panels being left open: a. General Electric breaker panel on the inside wall at the mechanic shop. b. 110 volt electrical outlet junction box at the end of a flexible electrical cord on work table in north end of mechanic shop. c. The Tram-A-Lot baler, was in the process of waiting for a new electrical switch to be installed and the opening where the switch had been located was left open with live open with live electrical conductors present. The Square D Main Disconnect, Number 10 breaker and Number 03 breaker which supplied power to the Tram-A-Lot baler, was energized and was not locked out.