Violation Detail
Standard Cited: 19260451 F07 General requirements.
Inspection Nr: 394944.015
Citation: 01004A
Citation Type: Serious
Abatement Date: 07/12/2012 2
Initial Penalty: $2,000.00
Current Penalty: $1,400.00
Issuance Date: 06/27/2012
Nr Instances: 1
Nr Exposed: 5
Related Event Code (REC):
Gravity: 5
Report ID: 0215000
Contest Date: 07/13/2012
Final Order: 11/26/2012
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 11/26/2012 | $1,400.00 | 07/12/2012 | Serious | |
| Penalty | C: Contested | 07/16/2012 | $2,000.00 | 07/12/2012 | Serious | |
| Penalty | Z: Issued | 06/27/2012 | $2,000.00 | 07/12/2012 | Serious |
Text For Citation: 01 Item/Group: 004A Hazard:
29 CFR 1926.451(f)(7): Scaffolds shall be erected, moved, dismantled, or altered only under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration. Such activities shall be performed only by experienced and trained employees selected for such work by the competent person. a) Cellar level, northeast side: Employees erected four 1-frame-high supported scaffold, which were used to build CMU walls with cinder blocks for an elevator shaft. The scaffolds were not erected under the supervision and direction of a competent person. The employer did not have a competent person on site for the scaffold erection. On or about 04/18/12. NOTE: IN ADDITION TO CERTIFICATION OF ABATEMENT, THE EMPLOYER IS REQUIRED TO SUBMIT DOCUMENTATION OF ABATEMENT FOR THIS ITEM. FAILURE TO COMPLY MAY RESULT IN AN ADDITIONAL PENALTY OF $1,000 AS PER 29 CFR 1903.19.