Violation Detail
Standard Cited: 19260451 B01 General requirements.
Inspection Nr: 394944.015
Citation: 01002A
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $2,000.00
Current Penalty: $2,000.00
Issuance Date: 06/27/2012
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity: 5
Report ID: 0215000
Contest Date: 07/13/2012
Final Order: 11/26/2012
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 11/26/2012 | $2,000.00 | Serious | ||
| Penalty | C: Contested | 07/16/2012 | $2,000.00 | Serious | ||
| Penalty | Z: Issued | 06/27/2012 | $2,000.00 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds shall be fully planked or decked between the front uprights and the guardrail supports. a) Cellar level, northeast side: Employees were working on the platforms of 1-frame-high supported scaffolds. The working platforms were not fully planked or decked between the front uprights and the guardrail supports. On or about 04/18/12. Note: Because abatement of this violation is already documented in the inspection case file, the employer need not submit certification of abatement for this violation as normally required by 29 CFR 1903.19.