Violation Detail
Standard Cited: 19100269 A02 I Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 385603.015
Citation: 01002
Citation Type: Serious
Abatement Date: 09/28/2012 2
Initial Penalty: $4,900.00
Current Penalty: $3,625.00
Issuance Date: 09/27/2012
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): A
Gravity: 10
Report ID: 0627700
Contest Date:
Final Order: 10/23/2012
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 10/23/2012 | $3,625.00 | 09/28/2012 | Serious | |
| Penalty | Z: Issued | 09/27/2012 | $4,900.00 | 09/28/2012 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.269(a)(2)(i): Employees were not trained in and familiar with the safety-related work practices, safety procedures, and other safety requirements in this section that pertain to their respective job assignments: On or about April 3, 2012, at a remote overhead powerline re-routing site, employees were allowed to work on a power transmission line without being properly trained on the recognition of specific safety precautions pertaining to their respective job assignments, exposing employees to the hazard of electricity.