Violation Detail
Standard Cited: 19100119 L02 IV Process safety management of highly hazardous chemicals.
Inspection Nr: 312412356
Citation: 03016
Citation Type: Other
Abatement Date: 06/01/2014 X
Initial Penalty: $3,000.00
Current Penalty: $1,500.00
Issuance Date: 04/28/2010
Nr Instances: 1
Nr Exposed: 24
Related Event Code (REC):
Gravity: 10
Report ID: 0854910
Contest Date: 05/27/2010
Final Order: 10/23/2013
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | P: Petition to Mod Abatement | 04/18/2014 | $1,500.00 | 06/01/2014 | Other | |
Penalty | F: Formal Settlement | 10/23/2013 | $1,500.00 | 02/20/2014 | Other | |
Penalty | Z: Issued | 04/28/2010 | $3,000.00 | 06/03/2010 | Serious |
Text For Citation: 03 Item/Group: 016 Hazard: REFINERY
29 CFR 1910.119(l)(2)(iv) The procedures shall assure that the following considerations are addressed prior to any change: Necessary time period for the change; A. The employer did not ensure that procedures addressed specific considerations prior to any change; specifically the necessary time period for the change. This violation was identified during inspections of the facility from November 2009 to March 2010, Silver Eagle Refining Inc., 2355 South 1100 West, Woods Cross, UT, 84087. Review of the Management of Change (MOC) policy provided no information on the necessary time periods for temporary changes. MOC's including, but not limited to, MOC #153, dated 3/7/08, MOC #179, dated 5/1/08, MOC #278, dated 3/13/09, and MOC 321, dated 7/23/09 were all identified as a temporary change. Management of Change policy provided as MDDW 1- UOSH-60 0001-0003 did not identify the necessary time period for the change. By not determining and documenting an appropriate time frame for temporary changes, work may potentially not be completed or become permanent without proper design. Inadequately design equipment can fail exposing employees to serious injury or death. This may be a system-wide occurrence that requires evaluation of all MOC's, management of change policies, and procedures throughout the facility.