Violation Detail
Standard Cited: 19100305 A02 X Wiring methods, components, and equipment for general use.
This violation item has been deleted.
Inspection Nr: 1736181.015
Citation: 01002F
Citation Type: Serious
Abatement Date: 08/16/2024 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/30/2024
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 1
Report ID: 0316700
Contest Date:
Final Order: 08/21/2024
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 08/21/2024 | $0.00 | 08/16/2024 | Serious | |
| Penalty | Z: Issued | 07/30/2024 | $0.00 | 08/16/2024 | Serious |
Text For Citation: 01 Item/Group: 002F Hazard:
29 CFR 1910.305(a)(2)(x): Flexible cords were not protected from accidental damage, as might be caused, for example, by sharp corners, projections, and doorways or other pinch points. a) 510 Kenhorst Plaza, READING, PA 19607 - An orange flexible power cord was run through, over, and under-counter edges and dividers. The origin cannot be determined due to the duct tape securing the cords to the floor. It enters the under-counter space and continues under the counter. It terminates into a white relocatable power tap, on or about March 21, 2024. Abatement certification required within 15 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.