Violation Detail
Standard Cited: 19100178 P01 Powered industrial trucks.
Inspection Nr: 1657166.015
Citation: 01002
Citation Type: Serious
Abatement Date: 10/03/2023 2
Initial Penalty: $5,313.00
Current Penalty: $1,400.00
Issuance Date: 09/07/2023
Nr Instances: 3
Nr Exposed: 15
Related Event Code (REC): C
Gravity: 5
Report ID: 0336000
Contest Date:
Final Order: 09/26/2023
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 09/26/2023 | $1,400.00 | 10/03/2023 | Serious | |
| Penalty | Z: Issued | 09/07/2023 | $5,313.00 | 10/03/2023 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.178(p)(1): Powered industrial truck(s) found to be in need of repair, defective, or in any way unsafe had not been taken out of service until restored to safe operating condition(s): a.) Warren Industries, Inc.; warehouse - On or about 3/16/22, and times prior thereto, the rear tire on Caterpillar propane forklift #158 was damaged. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Translate