Violation Detail
Standard Cited: 19260451 A01 General requirements.
Inspection Nr: 1575603.015
Citation: 01001A
Citation Type: Serious
Abatement Date: 06/27/2022 2
Initial Penalty: $11,747.00
Current Penalty: $11,747.00
Issuance Date: 06/10/2022
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): A
Gravity: 10
Report ID: 0523300
Contest Date:
Final Order: 07/12/2022
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/12/2022 | $11,747.00 | 06/27/2022 | Serious | |
| Penalty | Z: Issued | 06/10/2022 | $11,747.00 | 06/27/2022 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1926.451(a)(1):Scaffold(s) and scaffold(s) component(s) were not capable of supporting, without failure, its own weight and at least four times the maximum intended load applied or transmitted to it: On or about December 22, 2021, scaffold(s) and scaffold(s) component(s) located at the site at Lot No. 13 15th Ave Nekoosa, WI 54457 were not capable of supporting, without failure, its own weight and at least four times the maximum intended load applied or transmitted to it.
Translate