Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1564165.015
Citation: 01002
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $9,687.00
Current Penalty: $4,843.00
Issuance Date: 02/11/2022
Nr Instances: 1
Nr Exposed: 40
Related Event Code (REC):
Gravity: 5
Report ID: 0521100
Contest Date:
Final Order: 03/10/2022
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 03/10/2022 | $4,843.00 | Serious | ||
| Penalty | Z: Issued | 02/11/2022 | $9,687.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(6)(i):The employer shall conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirements of this standard are being followed. a. On or about November 17, 2021, the Apogee Wausau Group, Inc. dba Wausau Window and Wall Systems had not performed a periodic inspection of it's the energy control procedure for the 1275 Haas VF2 at least annually to ensure that the procedure and requirements of this standard were being followed. b. On or about November 17, 2021, the Apogee Wausau Group, Inc. dba Wausau Window and Wall Systems had not performed a periodic inspection of it's the energy control procedure for the Elumatec SB2151 at least annually to ensure that the procedure and requirements of this standard were being followed. c. On or about November 17, 2021, the Apogee Wausau Group, Inc. dba Wausau Window and Wall Systems had not performed a periodic inspection of it's the energy control procedure for the Graule Mill, Machine # 1284 at least annually to ensure that the procedure and requirements of this standard were being followed. d. On or about November 17, 2021, the Apogee Wausau Group, Inc. dba Wausau Window and Wall Systems had not performed a periodic inspection of it's the energy control procedure for the EW Bliss Punch Press, Machine # 1524 at least annually to ensure that the procedure and requirements of this standard were being followed. e. On or about November 17, 2021, the Apogee Wausau Group, Inc. dba Wausau Window and Wall Systems had not performed a periodic inspection of it's the energy control procedure for the Kaltenbach Auto Saw, Machine #1891 at least annually to ensure that the procedure and requirements of this standard were being followed. f. On or about November 17, 2021, the Apogee Wausau Group, Inc. dba Wausau Window and Wall Systems had not performed a periodic inspection of it's the energy control procedure for the Emmegi Double Saw, Machine # 1760 at least annually to ensure that the procedure and requirements of this standard were being followed. g. On or about November 17, 2021, the Apogee Wausau Group, Inc. dba Wausau Window and Wall Systems had not performed a periodic inspection of it's the energy control procedure for the Cope Saw, Machine # 1860 at least annually to ensure that the procedure and requirements of this standard were being followed. h. On or about November 17, 2021, the Apogee Wausau Group, Inc. dba Wausau Window and Wall Systems had not performed a periodic inspection of it's the energy control procedure for the Mecal Geos, Machine # 1279 at least annually to ensure that the procedure and requirements of this standard were being followed. i. On or about November 17, 2021, the Apogee Wausau Group, Inc. dba Wausau Window and Wall Systems had not performed a periodic inspection of it's the energy control procedure for the Mecal Kosmos at least annually to ensure that the procedure and requirements of this standard were being followed.
Translate