Violation Detail
Standard Cited: 19260451 C01 III General requirements.
Inspection Nr: 1560754.015
Citation: 01002
Citation Type: Serious
Abatement Date: 04/06/2022 2
Initial Penalty: $4,351.00
Current Penalty: $2,610.00
Issuance Date: 03/14/2022
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 10
Report ID: 0626000
Contest Date:
Final Order: 04/07/2022
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/07/2022 | $2,610.00 | 04/06/2022 | Serious | |
Penalty | Z: Issued | 03/14/2022 | $4,351.00 | 04/06/2022 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.451(c)(1)(iii): Ties, guys, braces, or outriggers were not installed to prevent the tipping of supported scaffolds in all circumstances where an eccentric load, such as a cantilevered work platform, was applied or was transmitted to the scaffold: On or about October 25, 2021 and times prior there to, North exterior wall of a multi-family dwelling, the employer failed to ensure a supported mobile scaffold was braced prior to allowing employees to conduct structural repair while using the scaffold.