Standard Cited: 19100303 B07 General.

Inspection Nr: 1550324.015

Citation: 01006

Citation Type: Serious

Abatement Status: Corrected During Inspection

Initial Penalty: $14,502.00

Current Penalty: $14,502.00

Issuance Date: 02/23/2022

Nr Instances: 1

Nr Exposed: 1

Abatement Date:

Gravity: 10

Report ID: 0213400

Contest Date: 03/21/2022

Final Order: 08/31/2023

Related Event Code (REC): A

Emphasis:


Penalty and Failure to Abate Event History
Type Latest Event Event Date Penalty Abatement Due Date Citation Type Failure to Abate Inspection
Penalty J: ALJ Decision 08/31/2023 $14,502.00   Serious  
Penalty C: Contested 03/21/2022 $14,502.00   Serious  
Penalty Z: Issued 02/23/2022 $14,502.00   Serious  

Text For Citation: 01 Item/Group: 006 Hazard:

29 CFR 1910.303(b)(7): Mechanical execution of work. Electric equipment was not installed in a neat, safe and workmanlike manner. A) FAZTEC Industries - 200 Bloomfield Ave, Staten Island NY 10314 Damaged cable insulation of conductors (exposed copper) operating at 460VAC were not protected with an insulator equivalent to that of cables original insulator or with an insulating device for that purpose. Condition noted on or about August 27, 2021

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.