Violation Detail
Standard Cited: 19100147 C06 I C The control of hazardous energy (lockout/tagout).
Inspection Nr: 1515904.015
Citation: 01001A
Citation Type: Serious
Abatement Date: 08/17/2021 2
Initial Penalty: $13,653.00
Current Penalty: $12,000.00
Issuance Date: 07/09/2021
Nr Instances: 2
Nr Exposed: 2
Related Event Code (REC):
Gravity: 10
Report ID: 0521700
Contest Date:
Final Order: 08/03/2021
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/03/2021 | $12,000.00 | 08/17/2021 | Serious | |
Penalty | Z: Issued | 07/09/2021 | $13,653.00 | 08/04/2021 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.147(c)(6)(i)(C): Where lockout was used for energy control, the periodic inspection did not include a review between the inspector and each authorized employee, of that employee's responsibilities under the energy control procedure being inspected: a.) Line 3 Rademacher - On or about January 3, 2021, an authorized employee performed preventive maintenance on the line 3 Rademacher machine (order no. 7700283). The employer failed to provide a periodic inspection that included a review between the inspector and each authorized employee and the employee's responsibility under the energy control procedure. b.) Line 3 Rademacher - On or about February 17, 2021, an authorized employee performed the service task of dismantling the laminator guard on the line 3 Rademacher machine. The employer failed to provide a periodic inspection that included a review between the inspector and each authorized employee and the employee's responsibility under the energy control procedure.