Violation Detail
Standard Cited: 19260416 A03 General requirements.
Inspection Nr: 1514179.015
Citation: 01002
Citation Type: Serious
Abatement Date: 04/20/2021 2
Initial Penalty: $5,461.00
Current Penalty: $5,461.00
Issuance Date: 03/25/2021
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity: 10
Report ID: 0418800
Contest Date:
Final Order: 04/26/2021
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 03/25/2021 | $5,461.00 | 04/20/2021 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.416(a)(3): Before work began, the employer did not ascertain by inquiry, direct observation, or by instruments, whether any part of an energized electric power circuit, exposed or concealed, was so located that the performance of the work could bring any person, tool, or machine into pysical or electrical contact with the electric power circuit: On or about January 5, 2021, at 2782 NE 31 Court, Lighthouse Point, Florida 33064. employer didn't ensure that power line were identified, marked and advised employees of electrocution hazard when employees were performing metal sheet roof installation next to a 13.2 KV overhead power lines.