Violation Detail
Standard Cited: 19261101 G08 III C Asbestos
Inspection Nr: 1493558.015
Citation: 01006
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $4,096.00
Current Penalty: $1,720.32
Issuance Date: 03/15/2021
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 04/08/2021
Gravity: 10
Report ID: 0214500
Contest Date: 04/16/2021
Final Order: 12/23/2021
Related Event Code (REC):
Emphasis:
Substance: 9020
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | J: ALJ Decision | 12/23/2021 | $1,720.32 | 04/08/2021 | Serious | |
| Penalty | C: Contested | 04/20/2021 | $4,096.00 | 04/08/2021 | Serious | |
| Penalty | Z: Issued | 03/15/2021 | $4,096.00 | 04/08/2021 | Serious |
Text For Citation: 01 Item/Group: 006 Hazard:
29 CFR 1926.1101(g)(8)(iii)(C):Unwrapped or unbagged panels or shingles were not immediately lowered to the ground via covered dusttight chute, crane or hoist, or placed in an impervious waste bag or wrapped in plastic sheeting and lowered to the ground no later than the end of the work shift: a) Exterior Rear of Single Family Frame Home: Transite asbestos panels, containing 15% chrysotile asbestos were removed by hand, using a flat bar tool, on a two story residential home. The employer did not ensure that transite asbestos containing panels were lowered to the ground and placed in an impervious waste bag, or wrapped in plastic sheeting, on or about 9/15/20.