Violation Detail
Standard Cited: 19100147 C04 II B The control of hazardous energy (lockout/tagout).
Inspection Nr: 1482899.015
Citation: 01001A
Citation Type: Other
Abatement Date: 10/16/2020 2
Initial Penalty: $10,603.00
Current Penalty: $3,900.00
Issuance Date: 10/06/2020
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 5
Report ID: 0524500
Contest Date:
Final Order: 11/03/2020
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 11/03/2020 | $3,900.00 | 10/16/2020 | Other | |
| Penalty | Z: Issued | 10/06/2020 | $10,603.00 | 10/16/2020 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.147(c)(4)(ii)(B): The energy control procedures did not clearly and specifically outline the steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy: On or about July 7, 2020, an employee utilized the machine specific lockout procedure for PB 33, and the lockout procedure did not contain specific procedural steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy.