Violation Detail
Standard Cited: 19100147 C06 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1470001.015
Citation: 01001
Citation Type: Serious
Abatement Date: 08/20/2020 2
Initial Penalty: $13,494.00
Current Penalty: $8,096.40
Issuance Date: 07/06/2020
Nr Instances: 7
Nr Exposed: 38
Related Event Code (REC):
Gravity: 10
Report ID: 0418100
Contest Date:
Final Order: 07/17/2020
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/17/2020 | $8,096.40 | 08/20/2020 | Serious | |
| Penalty | Z: Issued | 07/06/2020 | $13,494.00 | 08/20/2020 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(6)(ii): The employer did not certify that periodic inspections of the energy control procedures had been performed. On 3/16/20, at the Elberton location, the employer did not ensure a periodic inspection was performed of the Lockout Program at the facility. New equipment had been added to the facility but no procedure had been documented and other procedures went without review. The following deficiencies were identified: a - Elberton Vertical Reciprocating Conveyor - implemented 4/25/2015 (no procedure existed at the time of inspection) b - Sifter Elberton Breader Recovery - implemented 8/8/2016 (no procedure existed at the time of inspection) c - Elberton 14 Pallet Inverter - implemented 9/26/2018 (no procedure existed at the time of inspection) d - Elberton 7 Boiler replacement - implemented 12/29/2017 (no procedure existed at the time of inspection) e - Elberton Taper Project - implemented 11/16/2018 (no procedure existed at the time of inspection) f - 3 Anritsu XR75 Package X-Ray Machines Line implemented 4 1/9/2020, Line 5 implemented 3/2019, Line 6 implemented 7/2019 (no procedure existed at the time of inspection) g Line 6 implemented 7/2019 (no procedure existed at time of inspection)