Violation Detail
Standard Cited: 19260502 D06 IV Fall protection systems criteria and practices.
Inspection Nr: 1465028.015
Citation: 02001
Citation Type: Serious
Abatement Date: 06/23/2020 2
Initial Penalty: $4,048.00
Current Penalty: $2,833.60
Issuance Date: 05/13/2020
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 10
Report ID: 0112600
Contest Date:
Final Order: 06/11/2020
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/11/2020 | $2,833.60 | 06/23/2020 | Serious | |
| Penalty | Z: Issued | 05/13/2020 | $4,048.00 | 06/23/2020 | Serious |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1926.502(d)(6)(iv): Unless the snap hook is a locking type and designed for the following connections, snap hooks shall not be engaged to a horizontal lifeline: a) 171 Main St., Westfield, MA: On or about February, 25 2020 an employees was observed to have their snap hook engaged to a horizontal lifeline. Specific abatement documentation that this violation has been corrected must be provided within 10 days of the abatement in accordance with 29CFR1903.19(d)(1).
Translate