Violation Detail
Standard Cited: 19100147 C06 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1461599.015
Citation: 01003
Citation Type: Other
Abatement Date: 04/06/2020 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 02/19/2020
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity:
Report ID: 0729300
Contest Date:
Final Order: 03/09/2020
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 03/09/2020 | $0.00 | 04/06/2020 | Other | |
| Penalty | Z: Issued | 02/19/2020 | $0.00 | 04/06/2020 | Other |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.147(c)(6)(ii): The periodic inspection certification of energy control procedures did not contain the required documentation on identification of the machine or equipment, inspection date, employees included, and the person performing the inspection: At 9816 Evergreen Industrial Drive, St. Louis, Missouri, the documentation for the annual inspection for machinery such as but not limited to the Plastic Injection Molding Machine, m/n G-100T, s/n 7488, included just the initials of the inspector. This violation was noted on 02/11/20.
Translate