Standard Cited: 19100147 C04 II D The control of hazardous energy (lockout/tagout).
Inspection Nr: 1460438.015
Citation: 03002C
Citation Type: Other
Abatement Date: 01/31/2022 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 06/01/2020
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity: 5
Report ID: 0418300
Contest Date: 06/30/2020
Final Order: 01/19/2022
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | J: ALJ Decision | 01/19/2022 | $0.00 | 01/31/2022 | Other | |
| Penalty | C: Contested | 07/07/2020 | $0.00 | 06/25/2020 | Serious | |
| Penalty | Z: Issued | 06/01/2020 | $0.00 | 06/25/2020 | Serious |
Text For Citation: 03 Item/Group: 002C Hazard:
29 CFR 1910.147(c)(4)(ii)(D): The energy control procedures did not clearly and specifically outline the requirements for testing a machine or equipment to determine and verify the effectiveness of lockout devices, tagout devices, and other energy control measures: (a) On or about February 03, 2020 - Grinding areas, employees were exposed to struck-by hazards when a lockout/tagout (LOTO) procedure such as, but not limited to, the Erema Offline Grinder Operation (PU-WI-PET-EOLG-001) did not specify how to verify that the lock placed on the main control panel cabinet was effective. Lockout/tagout procedures such as, but not limited to, Offline Grinder Feeder (PPX-975), Offline Grinder Motor (PPX-072), Offline Conveying Blower (PPX-973), and Offline Grinder Hydraulic Motor (PPX-974) did not clearly or specifically describe how to attempt to restart the machines.