Violation Detail
Standard Cited: 19150089 G02
This violation item has been deleted.
Inspection Nr: 1450843.015
Citation: 01002
Citation Type: Serious
Abatement Date: 03/31/2020 2
Initial Penalty: $13,494.00
Current Penalty: $0.00
Issuance Date: 03/24/2020
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 10
Report ID: 0420300
Contest Date:
Final Order: 04/14/2020
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/14/2020 | $0.00 | 03/31/2020 | Serious | |
Penalty | Z: Issued | 03/24/2020 | $13,494.00 | 03/31/2020 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1915.89(g)(2): The employer shall ensure that the authorized employee, or the primary authorized employee in a group lockout/tags-plus application, continues verifying deenergization and isolation while servicing the machinery, equipment, or system. a) The Electrical Gallery at Dry Dock #5: Employer did not ensure that two employees working on the electrical panel #F-12 continued to verify that the machinery, equipment, or system was still deenergized and all energy sources isolated.