Standard Cited: 19100147 C04 II B The control of hazardous energy (lockout/tagout).
Inspection Nr: 1437527.015
Citation: 01001A
Citation Type: Serious
Abatement Date: 04/16/2020 2
Initial Penalty: $13,494.00
Current Penalty: $13,494.00
Issuance Date: 03/12/2020
Nr Instances: 1
Nr Exposed: 16
Related Event Code (REC): R
Gravity: 10
Report ID: 0522500
Contest Date:
Final Order: 04/07/2020
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 03/12/2020 | $13,494.00 | 04/16/2020 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.147(c)(4): Energy control procedure. 29 CFR 1910.147(c)(4)(ii): The procedures shall clearly and specifically outline the scope, purpose, authorization, rules, and techniques to be utilized for the control of hazardous energy, and the means to enforce compliance including, but not limited to, the following: 29 CFR 1910.147(c)(4)(ii)(B): Specific procedural steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy; a. On or about October 15, 2019, the employer's energy control procedures for Weld department Tunnel Lines did not include specific procedural steps to address potential stored mechanical energy associated with jig cart set-up activities. Employees performed required duties covered by this part that involved stored mechanical energy exposure when jig cart suspension occurred due to positioning pin misalignment during the activity. On October 7, 2019, an employee suffered a partial finger amputation related to the performance of the jig cart set-up task on Tunnel Line 1 at station 10.