Violation Detail
Standard Cited: 19100147 C04 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1436905.015
Citation: 01001
Citation Type: Serious
Abatement Date: 12/03/2019 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 10/29/2019
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): A
Gravity: 10
Report ID: 0420300
Contest Date:
Final Order: 11/22/2019
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 10/29/2019 | $0.00 | 12/03/2019 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(ii): The energy control procedures did not clearly and specifically outline the scope, purpose, authorization, rules, and techniques to be utilized for the control of hazardous energy, including, but not limited to Items A-D of this section: FRC East, Bldg. Askar Shop #69140, Safe Site B-10: On or about October 8, 2019, the energy control procedure, for the LSIS 22, failed to clearly identify all of the specific steps to be followed by employees to isolate the stacker lift cage and control the release of stored energy. The procedure also lacked specific steps to block, clamp or restrain the lift cage along the mast of the machine prior to performing maintenance activity and specific verification steps to take in order to determine the effectiveness of the energy control measures. ABATEMENT DOCUMENTATION REQUIRED