Violation Detail
Standard Cited: 19260251 A02 I Rigging equipment for material handling.
Inspection Nr: 1436902.015
Citation: 01001
Citation Type: Other
Abatement Date: 03/18/2020 2
Initial Penalty: $757.00
Current Penalty: $757.00
Issuance Date: 02/19/2020
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): R
Gravity:
Report ID: 0627100
Contest Date:
Final Order: 03/16/2020
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 02/19/2020 | $757.00 | 03/18/2020 | Other |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.251(a)(2)(i): The employer failed to ensure rigging equipment had permanently affixed and legible identification markings as prescribed by the manufacturer that indicate the recommended safe working load. On October 8, 2019, at the construction site, the employer did not ensure rigging equipment had permanently affixed and legible identification markings as prescribed by the manufacturer that indicate the recommended safe working load. Employees were installing concrete storm drainage pipes and were exposed to struck by hazards.