Standard Cited: 19100119 J04 II Process safety management of highly hazardous chemicals.
This violation item has been deleted.
Inspection Nr: 1422114.015
Citation: 01001B
Citation Type: Serious
Abatement Date: 02/13/2020
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 01/27/2020
Nr Instances: 1
Nr Exposed: 5
Related Event Code (REC):
Gravity: 10
Report ID: 0626600
Contest Date:
Final Order: 03/06/2020
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 03/06/2020 | $0.00 | 02/13/2020 | Serious | |
| Penalty | Z: Issued | 01/27/2020 | $0.00 | 02/13/2020 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.119(j)(4)(ii): Inspection and testing procedures did not follow recognized and generally accepted good engineering practices: On or about August 1, 2019, in the N-Area of the Cold Ends unit at the ExxonMobil Baytown Olefins Plant, the employer did not conduct baseline thickness measurements as stipulated in RAGAGEP such as API 570.