Violation Detail
Standard Cited: 19100147 C06 I C The control of hazardous energy (lockout/tagout).
Inspection Nr: 1417032.015
Citation: 01002B
Citation Type: Serious
Abatement Date: 01/28/2020 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 12/09/2019
Nr Instances: 3
Nr Exposed: 1
Related Event Code (REC): R
Gravity: 10
Report ID: 0112600
Contest Date:
Final Order: 12/19/2019
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 12/19/2019 | $0.00 | 01/28/2020 | Serious | |
| Penalty | Z: Issued | 12/09/2019 | $0.00 | 01/28/2020 | Serious |
Text For Citation: 01 Item/Group: 002B Hazard:
29 CFR 1910.147(c)(6)(i)(C): Where lockout was used for energy control, the periodic inspection did not include a review, between the inspector and each authorized employee, of that employee's responsibilities under the energy control procedure being inspected. (a) Site: In the Compounding Area, Building A, Lower Level, Lines 1-3 and Building B, Lower Level, Lines 4-5 in the production area at the facility located at 170 Pioneer Drive, Leominster, MA 01453: On 7/22/2019, and at times earlier, where lockout was used for energy control for the Dicer, the periodic inspection did not include a review, between the inspector and each authorized employee, of that employee's responsibilities under the energy control procedure being inspected.
Translate