Violation Detail
Standard Cited: 19100334 A02 I Use of equipment.
Inspection Nr: 1401254.015
Citation: 03005
Citation Type: Other
Abatement Date: 11/15/2019 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 11/08/2019
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity:
Report ID: 0936400
Contest Date:
Final Order: 12/26/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/26/2019 | $0.00 | 11/15/2019 | Other | |
Penalty | Z: Issued | 11/08/2019 | $0.00 | 11/15/2019 | Other |
Text For Citation: 03 Item/Group: 005 Hazard:
29 CFR 1910.334(a)(2)(i): Portable cord and plug connected equipment and flexible cord sets (extension cords) were not visually inspected before use on any shift for external defects (such as loose parts, deformed and missing pins, or damage to outer jacket or insulation) and for evidence of possible internal damage (such as pinched or crushed outer jacket): B Building- Employees were exposed to fire hazards where the Dayton 1000 pound crane used at the OCEM Press was powered with a extension cord that had damage to the outer jacket.