Violation Detail
Standard Cited: 19260752 D Site layout, site-specific erection plan and construction sequence.
Inspection Nr: 1388682.015
Citation: 01002
Citation Type: Serious
Abatement Date: 07/05/2019 2
Initial Penalty: $6,763.00
Current Penalty: $4,395.95
Issuance Date: 06/24/2019
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 5
Report ID: 0418300
Contest Date:
Final Order: 07/23/2019
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/23/2019 | $4,395.95 | 07/05/2019 | Serious | |
| Penalty | Z: Issued | 06/24/2019 | $6,763.00 | 07/05/2019 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1926.752(d): All hoisting operations in steel erection were not pre-planned to ensure that the requirements of 29 CFR 1926.753(d) are met: (a) On or about 03/05/2019 - Flaking Silo area, the employer did not appropriately plan for hoisting an overhead structural steel H-beam weighing approximately 3,528 pounds and is 12 feet in length.