Violation Detail
Standard Cited: 19100219 F01 I Mechanical power-transmission apparatus.
Inspection Nr: 1387132.015
Citation: 01001B
Citation Type: Serious
Abatement Date: 08/01/2019 2
Initial Penalty: $11,934.00
Current Penalty: $0.00
Issuance Date: 06/28/2019
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity: 10
Report ID: 0523400
Contest Date:
Final Order: 07/17/2019
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/17/2019 | $0.00 | 08/01/2019 | Serious | |
| Penalty | Z: Issued | 06/28/2019 | $11,934.00 | 08/01/2019 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.219(f)(1)(i): Gears which were seven (7) feet or less above the floor or platform were not guarded by a complete enclosure. (a) JMB Printing Press #5: The employer did not insure a complete enclosure barrier guard or other guarding method(s) was properly implemented for the four (4) separate color stations on the printing press. This allowed the employee(s) to access the drive gears in an energized state and exposed the employee(s) to ingoing nip point, crushing hazard and amputation injury.