Standard Cited: 19100219 M01 Mechanical power-transmission apparatus.
Inspection Nr: 1380992.015
Citation: 01001
Citation Type: Serious
Abatement Date: 04/03/2019 2
Initial Penalty: $7,084.00
Current Penalty: $7,084.00
Issuance Date: 03/08/2019
Nr Instances: 2
Nr Exposed: 7
Related Event Code (REC): R
Gravity: 5
Report ID: 0316700
Contest Date:
Final Order: 03/22/2019
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 03/22/2019 | $7,084.00 | 04/03/2019 | Serious | |
| Penalty | Z: Issued | 03/08/2019 | $7,084.00 | 04/03/2019 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.219(m)(1): Standard guards were not securely fastened to the frame of the machine. a) Line 1 Stamper - The protective guard was not securely fastened to the frame of the Line 1 Stamper and employees were were exposed to caught-in hazards, on or about February 26th, 2019. b) Line 2 Stamper - The protective guard was not securely fastened to the frame of the Line 2 Stamper and were exposed to caught-in hazards, on or about February 26th, 2019. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.