Violation Detail
Standard Cited: 19100179 N03 X Overhead and gantry cranes.
Inspection Nr: 1374747.015
Citation: 01001
Citation Type: Serious
Abatement Date: 03/22/2019 2
Initial Penalty: $11,934.00
Current Penalty: $7,160.40
Issuance Date: 03/01/2019
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 10
Report ID: 0636900
Contest Date:
Final Order: 03/21/2019
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 03/21/2019 | $7,160.40 | 03/22/2019 | Serious | |
| Penalty | Z: Issued | 03/01/2019 | $11,934.00 | 03/22/2019 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.179(n)(3)(x): The employer did not insure that the operator does not leave his position at the controls while the load is suspended: On or about January 30, the employer did not ensure the crane operators maintain positions at the pendent controls while the cranes load was suspended.