Violation Detail
Standard Cited: 19260251 C04 IV Rigging equipment for material handling.
Inspection Nr: 1362917.015
Citation: 01001
Citation Type: Other
Abatement Date: 06/13/2019 2
Initial Penalty: $6,630.00
Current Penalty: $3,000.00
Issuance Date: 05/23/2019
Nr Instances: 2
Nr Exposed: 30
Related Event Code (REC):
Gravity:
Report ID: 0134000
Contest Date:
Final Order: 06/14/2019
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 06/14/2019 | $3,000.00 | 06/13/2019 | Other | |
| Penalty | Z: Issued | 05/23/2019 | $6,630.00 | 06/13/2019 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.251(c)(4)(iv): Wire rope(s) were used in which the rope(s) showed signs of defect(s): 1 Pearce Memorial Drive, Saugus, MA a) On or about November 27, 2018, wire rope used as part of a multi-pick lift showed signs of birdcaging, and was not taken out of service.