Violation Detail
Standard Cited: 19260850 A Preparatory operations.
Inspection Nr: 1359315.015
Citation: 01001
Citation Type: Other
Abatement Date: 03/29/2019 2
Initial Penalty: $13,260.00
Current Penalty: $13,260.00
Issuance Date: 03/05/2019
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): R
Gravity:
Report ID: 0418300
Contest Date:
Final Order: 04/01/2019
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/01/2019 | $13,260.00 | 03/29/2019 | Other | |
| Penalty | Z: Issued | 03/05/2019 | $13,260.00 | 03/29/2019 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.850(a): An engineering survey was not performed by a competent person to determine the conditions of the framing floors and walls and the possibility of unplanned collapse of any portion of the structure prior to permitting employees to start demolition operations: (a) On or about 11/03/2018 - Debarker discharge area, chipper feed conveyor structure, an engineering survey was not documented prior to the demolition of the structural support steel where the last remaining column was overloaded exposing employees to struck-by and/or crushed-by hazards.