Violation Detail
Standard Cited: 19100147 D06 The control of hazardous energy (lockout/tagout).
Inspection Nr: 1354441.015
Citation: 02001
Citation Type: Serious
Abatement Date: 05/11/2020 2
Initial Penalty: $0.00
Current Penalty: $9,282.00
Issuance Date: 02/05/2019
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity:
Report ID: 0522500
Contest Date: 02/21/2019
Final Order: 05/18/2020
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | J: ALJ Decision | 05/18/2020 | $9,282.00 | 05/11/2020 | Serious | |
| Penalty | C: Contested | 02/25/2019 | $0.00 | 02/25/2019 | Other | |
| Penalty | Z: Issued | 02/05/2019 | $0.00 | 02/25/2019 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.147(d)(6): Verification of isolation. Prior to starting work on machines or equipment that have been locked out or tagged out, the authorized employee shall verify that isolation and deenergization of the machine or equipment have been accomplished. a. On or about October 13, 2018, located in the INF Department on the Grinder Line at Amsted Rail in Groveport, Ohio, the employer did not ensure all authorized employees performing a cylinder change on FR-75 verified the isolation and deenergization of the upender.