Violation Detail
Standard Cited: 19260417 A Lockout and tagging of circuits.
Inspection Nr: 1352641.015
Citation: 02001
Citation Type: Other
Abatement Date: 03/27/2019 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/21/2019
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity:
Report ID: 0316100
Contest Date: 04/10/2019
Final Order: 08/28/2019
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 08/28/2019 | $0.00 | 03/27/2019 | Other | |
| Penalty | C: Contested | 04/12/2019 | $0.00 | 03/27/2019 | Other | |
| Penalty | Z: Issued | 03/21/2019 | $0.00 | 03/27/2019 | Other |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1926.417(a): Controls that were to be deactivated during the course of work on energized or de-energized equipment or circuits were not tagged: a) Solar Pad #26 and #34 Transformers - An employee was installing new grounds on the secondary side of four transformers and the selector switches which de-energized the service were not provided with a tag, 277/480 volt service, on or about 09/28/2018. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet).
Translate