Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1349985.015
Citation: 01002
Citation Type: Other
Abatement Date: 01/09/2019 2
Initial Penalty: $4,398.00
Current Penalty: $3,078.60
Issuance Date: 12/19/2018
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity:
Report ID: 0418300
Contest Date:
Final Order: 01/14/2019
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/14/2019 | $3,078.60 | 01/09/2019 | Other | |
| Penalty | Z: Issued | 12/19/2018 | $4,398.00 | 01/09/2019 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: (a) On or about 09/20/2018 - Plant area, periodic inspections were not conducted for equipment such as, but not limited to, Reford 22 machines, Reford 43 machines, Reford 16 machines, and Core Ovens.