Violation Detail
Standard Cited: 19100147 C04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1342170.015
Citation: 01001
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $11,642.00
Current Penalty: $10,000.00
Issuance Date: 10/11/2018
Nr Instances: 1
Nr Exposed: 16
Related Event Code (REC): R
Gravity: 10
Report ID: 0418300
Contest Date:
Final Order: 11/09/2018
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 11/09/2018 | $10,000.00 | Serious | ||
| Penalty | Z: Issued | 10/11/2018 | $11,642.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section: a) On or about 08/21/2018 - Plant A, presser fat pump #2, a specific procedure was not documented, developed, and utilized for employees performing servicing and maintenance on the fat pump with electrical and pneumatic sources of energy.
Translate