Violation Detail
Standard Cited: 19100147 D05 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1334766.015
Citation: 01001
Citation Type: Other
Abatement Date: 12/24/2018 2
Initial Penalty: $12,934.00
Current Penalty: $12,934.00
Issuance Date: 12/14/2018
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): A
Gravity:
Report ID: 0625700
Contest Date:
Final Order: 01/08/2019
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/08/2019 | $12,934.00 | 12/24/2018 | Other | |
| Penalty | Z: Issued | 12/14/2018 | $12,934.00 | 12/24/2018 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(d)(5)(ii): Where there was a possibility of re-accumulation of stored energy to a hazardous level, verification of isolation was not continued until the servicing or maintenance was completed, or until the possibility of such accumulation no longer exists. Sulphur Unit - On or about July 4, 2018, the employer did not ensure that a 4 inch 300# gate valve on equipment 77H-103 (hydrogen block valve) was bled out at the line opening to depressurized the line. Employees were exposed to a flash fire/explosion hazard.