Violation Detail
Standard Cited: 19100269 A04 I Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1319790.015
Citation: 01001
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $12,934.00
Current Penalty: $12,000.00
Issuance Date: 08/29/2018
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): R
Gravity: 10
Report ID: 0214200
Contest Date:
Final Order: 09/24/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/24/2018 | $12,000.00 | Serious | ||
Penalty | Z: Issued | 08/29/2018 | $12,934.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.269(a)(4)(i): The nominal voltages of electric lines and equipment was not determined before work on or near the lines or equipment is started: a) Kearny #12 gas compressor MCC The nominal voltage of lines located inside Siemens Motor Control Center (MCC) were not determined before trouble shooting of equipment was started. On 5/29/18, an employee removed a bolted panel and tested a high voltage line (4160 V) before knowing the nominal voltage, causing an arc flash. Condition occurred on or about 5/29/2018